📋Daftar HPS
📍 KOTA
MAROS
MAROS
📅 TAHUN
2026
2026
| KELOMPOK A |
A.1 — PEMBERSIHAN LAPANGAN (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| UPAH | |||||
| 1 | Pekerja | OH | 0,1000 | 200.000,00 | 20.000,00 |
| 2 | Mandor | OH | 0,0500 | 165.000,00 | 8.250,00 |
| Jumlah | 28.250,00 | ||||
| Jasa 10% | 2.825,00 | ||||
| Total | 31.075,00 | ||||
A.2 — PENGUKURAN DAN PEMASANGAN BOUWPLANK (M')
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Papan Kls II | M³ | 0,0070 | 4.620.000,00 | 32.340,00 |
| 2 | Kayu Balok Kls II | M³ | 0,0120 | 4.620.000,00 | 55.440,00 |
| 3 | Paku biasa 2"-5" | KG | 0,0200 | 21.780,00 | 435,60 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1000 | 200.000,00 | 20.000,00 |
| 2 | Tukang kayu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 125.590,60 | ||||
| Jasa 10% | 12.559,06 | ||||
| Total | 138.149,66 | ||||
A.3 — PEMBUATAN PAGAR PROYEK DARI KAYU TINGGI 2 M (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kaso 5/7 kayu kelas II | M3 | 0,0387 | 0,00 | 0,00 |
| 2 | Papan Kayu ukuran 2/20 cm | M3 | 0,0396 | 0,00 | 0,00 |
| 3 | Paku biasa 1/2"- 1" | KG | 0,5872 | 22.990,00 | 13.499,73 |
| 4 | Semen portland | KG | 26,4060 | 1.540,00 | 40.665,24 |
| 5 | Pasir beton | M³ | 61,5600 | 220.000,00 | 13.543.200,00 |
| Jumlah | 13.597.364,97 | ||||
| Jasa 10% | 1.359.736,50 | ||||
| Total | 14.957.101,46 | ||||
| KELOMPOK B |
B.1 — GALIAN TANAH BIASA 1 M (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| UPAH | |||||
| 1 | Pekerja | OH | 0,7500 | 200.000,00 | 150.000,00 |
| 2 | Mandor | OH | 0,0250 | 165.000,00 | 4.125,00 |
| Jumlah | 154.125,00 | ||||
| Jasa 10% | 15.412,50 | ||||
| Total | 169.537,50 | ||||
B.2 — URUGAN TANAH KEMBALI (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| UPAH | |||||
| 1 | Pekerja | OH | 0,2500 | 200.000,00 | 50.000,00 |
| 2 | Mandor | OH | 0,0083 | 165.000,00 | 1.369,50 |
| Jumlah | 51.369,50 | ||||
| Jasa 10% | 5.136,95 | ||||
| Total | 56.506,45 | ||||
B.3 — URUGAN PASIR (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pasir urug | M | 1,2000 | 121.000,00 | 145.200,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,3000 | 200.000,00 | 60.000,00 |
| 2 | Mandor | OH | 0,0100 | 165.000,00 | 1.650,00 |
| Jumlah | 206.850,00 | ||||
| Jasa 10% | 20.685,00 | ||||
| Total | 227.535,00 | ||||
B.4 — URUGAN TANAH MERAH (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Tanah merah | M³ | 1,2000 | 124.300,00 | 149.160,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,3000 | 200.000,00 | 60.000,00 |
| 2 | Mandor | OH | 0,0100 | 165.000,00 | 1.650,00 |
| Jumlah | 210.810,00 | ||||
| Jasa 10% | 21.081,00 | ||||
| Total | 231.891,00 | ||||
| KELOMPOK C |
C.1 — PASANGAN PONDASI 1:5 (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Batu belah 15/20 | M³ | 1,2000 | 242.000,00 | 290.400,00 |
| 2 | Pasir pasang | M³ | 0,5440 | 400.000,00 | 217.600,00 |
| 3 | Semen portland | KG | 136,0000 | 1.540,00 | 209.440,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,5000 | 200.000,00 | 300.000,00 |
| 2 | Tukang batu | OH | 0,7500 | 150.000,00 | 112.500,00 |
| 3 | Mandor | OH | 0,0750 | 165.000,00 | 12.375,00 |
| 4 | Kepala tukang | OH | 0,0750 | 155.000,00 | 11.625,00 |
| Jumlah | 1.153.940,00 | ||||
| Jasa 10% | 115.394,00 | ||||
| Total | 1.269.334,00 | ||||
C.2 — PASANGAN PONDASI BATU KOSONG (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Batu belah 15/20 | M³ | 1,2000 | 242.000,00 | 290.400,00 |
| 2 | Pasir urug | M | 0,4320 | 121.000,00 | 52.272,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,7800 | 200.000,00 | 156.000,00 |
| 2 | Tukang batu | OH | 0,3900 | 150.000,00 | 58.500,00 |
| 3 | Kepala tukang | OH | 0,0390 | 155.000,00 | 6.045,00 |
| 4 | Mandor | OH | 0,0390 | 165.000,00 | 6.435,00 |
| Jumlah | 569.652,00 | ||||
| Jasa 10% | 56.965,20 | ||||
| Total | 626.617,20 | ||||
| KELOMPOK D |
D.1 — PASANGAN BATA MERAH TEBAL 1/2 BATA 1 PC : 2 PS TIAP 1 M2 (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Bata merah | BH | 70,0000 | 990,00 | 69.300,00 |
| 2 | Semen portland | KG | 18,9500 | 1.540,00 | 29.183,00 |
| 3 | Pasir pasang | M³ | 0,0380 | 400.000,00 | 15.200,00 |
| UPAH | |||||
| 1 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 2 | Pekerja | OH | 0,3000 | 200.000,00 | 60.000,00 |
| 3 | Tukang batu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 4 | Mandor | OH | 0,0150 | 165.000,00 | 2.475,00 |
| Jumlah | 192.708,00 | ||||
| Jasa 10% | 19.270,80 | ||||
| Total | 211.978,80 | ||||
D.2 — PASANGAN BATA MERAH TEBAL 1/2 BATA 1 PC : 5 PS TIAP 1 M2 (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Bata merah | BH | 70,0000 | 990,00 | 69.300,00 |
| 2 | Semen portland | KG | 11,5000 | 1.540,00 | 17.710,00 |
| 3 | Pasir pasang | M³ | 0,0430 | 400.000,00 | 17.200,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,3000 | 200.000,00 | 60.000,00 |
| 2 | Tukang batu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0150 | 165.000,00 | 2.475,00 |
| Jumlah | 183.235,00 | ||||
| Jasa 10% | 18.323,50 | ||||
| Total | 201.558,50 | ||||
D.3 — PASANGAN DINDING ROSTER BATA MERAH 20 X 30 TIAP 1 M2 SPASI 1:3 (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Roster 20 x 30 cm | BH | 22,2200 | 29.282,00 | 650.646,04 |
| 2 | Semen portland | KG | 14,0000 | 1.540,00 | 21.560,00 |
| 3 | Pasir pasang | M³ | 0,0320 | 400.000,00 | 12.800,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,3000 | 200.000,00 | 60.000,00 |
| 2 | Tukang batu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0150 | 165.000,00 | 2.475,00 |
| Jumlah | 764.031,04 | ||||
| Jasa 10% | 76.403,10 | ||||
| Total | 840.434,14 | ||||
| KELOMPOK E |
E.1 — PLESTERAN 1 PC : 3 PS TEBAL 15 MM TIAP 1 M2 (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 7,7760 | 1.540,00 | 11.975,04 |
| 2 | Pasir pasang | M³ | 0,0230 | 400.000,00 | 9.200,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,3000 | 200.000,00 | 60.000,00 |
| 2 | Tukang batu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0150 | 165.000,00 | 2.475,00 |
| Jumlah | 108.475,04 | ||||
| Jasa 10% | 10.847,50 | ||||
| Total | 119.322,54 | ||||
E.2 — PLESTERAN 1 PC : 5 PS TEBAL 15 MM TIAP 1 M2 (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 5,1840 | 1.540,00 | 7.983,36 |
| 2 | Pasir pasang | M³ | 0,0260 | 400.000,00 | 10.400,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,3000 | 200.000,00 | 60.000,00 |
| 2 | Tukang batu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0150 | 165.000,00 | 2.475,00 |
| Jumlah | 105.683,36 | ||||
| Jasa 10% | 10.568,34 | ||||
| Total | 116.251,70 | ||||
E.3 — ACIAN 1 (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 3,2500 | 1.540,00 | 5.005,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2000 | 200.000,00 | 40.000,00 |
| 2 | Tukang batu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0100 | 165.000,00 | 1.650,00 |
| Jumlah | 63.205,00 | ||||
| Jasa 10% | 6.320,50 | ||||
| Total | 69.525,50 | ||||
| KELOMPOK F |
F.1 — PASANG KUSEN PINTU DAN JENDELA KAYU KLS I (M3)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Balok Kls I | M³ | 1,1000 | 12.000.000,00 | 13.200.000,00 |
| 2 | Paku biasa 2"-5" | KG | 1,2500 | 21.780,00 | 27.225,00 |
| 3 | Lem kayu | KG | 1,0000 | 35.090,00 | 35.090,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 7,0000 | 200.000,00 | 1.400.000,00 |
| 2 | Tukang kayu | OH | 21,0000 | 150.000,00 | 3.150.000,00 |
| 3 | Kepala tukang | OH | 2,1000 | 155.000,00 | 325.500,00 |
| 4 | Mandor | OH | 0,3500 | 165.000,00 | 57.750,00 |
| Jumlah | 18.195.565,00 | ||||
| Jasa 10% | 1.819.556,50 | ||||
| Total | 20.015.121,50 | ||||
F.2 — PASANG PINTU PANEL KAYU KLS I (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Papan Kls I | M³ | 0,0400 | 12.000.000,00 | 480.000,00 |
| 2 | Lem kayu | KG | 0,5000 | 35.090,00 | 17.545,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,0000 | 200.000,00 | 200.000,00 |
| 2 | Tukang kayu | OH | 3,0000 | 150.000,00 | 450.000,00 |
| 3 | Kepala tukang | OH | 0,3000 | 155.000,00 | 46.500,00 |
| 4 | Mandor | OH | 0,0500 | 165.000,00 | 8.250,00 |
| Jumlah | 1.202.295,00 | ||||
| Jasa 10% | 120.229,50 | ||||
| Total | 1.322.524,50 | ||||
F.3 — PASANG PINTU DAN JENDELA KACA KAYU KLS I (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Papan Kls I | M³ | 0,0240 | 12.000.000,00 | 288.000,00 |
| 2 | Kaca 5 mm | M² | 1,1000 | 159.500,00 | 175.450,00 |
| 3 | Lem kayu | KG | 0,3000 | 35.090,00 | 10.527,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,8000 | 200.000,00 | 160.000,00 |
| 2 | Tukang kayu | OH | 2,4000 | 150.000,00 | 360.000,00 |
| 3 | Kepala tukang | OH | 0,2400 | 155.000,00 | 37.200,00 |
| 4 | Mandor | OH | 0,0400 | 165.000,00 | 6.600,00 |
| Jumlah | 1.037.777,00 | ||||
| Jasa 10% | 103.777,70 | ||||
| Total | 1.141.554,70 | ||||
F.4 — PASANG LISPLANK WOOD EVLEN TIAP M' (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Wood Evlent | LBR | 0,2500 | 114.950,00 | 28.737,50 |
| 2 | Sekrup gypsum | BH | 4,0000 | 220,00 | 880,00 |
| UPAH | |||||
| 1 | Tukang kayu | OH | 0,0500 | 150.000,00 | 7.500,00 |
| 2 | Kepala tukang | OH | 0,0050 | 155.000,00 | 775,00 |
| 3 | Mandor | OH | 0,0054 | 165.000,00 | 891,00 |
| Jumlah | 38.783,50 | ||||
| Jasa 10% | 3.878,35 | ||||
| Total | 42.661,85 | ||||
| KELOMPOK G |
G.1 — LIST PLAFON KAYU PROFIL (M')
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu list profil | M' | 1,0500 | 6.050,00 | 6.352,50 |
| 2 | Paku biasa 1/2"- 1" | KG | 0,0100 | 22.990,00 | 229,90 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0500 | 200.000,00 | 10.000,00 |
| 2 | Tukang kayu | OH | 0,0500 | 150.000,00 | 7.500,00 |
| 3 | Kepala tukang | OH | 0,0050 | 155.000,00 | 775,00 |
| 4 | Mandor | OH | 0,0030 | 165.000,00 | 495,00 |
| Jumlah | 25.352,40 | ||||
| Jasa 10% | 2.535,24 | ||||
| Total | 27.887,64 | ||||
G.2 — LIST PLAFON GYPSUM (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | List Gypsum | M' | 1,1000 | 24.200,00 | 26.620,00 |
| 2 | Compound gypsum | 20kg/zak | 0,0350 | 83.490,00 | 2.922,15 |
| 3 | Alkasit | kg | 0,0035 | 20.570,00 | 72,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0500 | 200.000,00 | 10.000,00 |
| 2 | Tukang kayu | OH | 0,0500 | 150.000,00 | 7.500,00 |
| 3 | Kepala tukang | OH | 0,0050 | 155.000,00 | 775,00 |
| 4 | Mandor | OH | 0,0030 | 165.000,00 | 495,00 |
| Jumlah | 48.384,15 | ||||
| Jasa 10% | 4.838,41 | ||||
| Total | 53.222,56 | ||||
G.3 — PENUTUP PLAFON CALCIBOARD LENGKAP DGN RANGKA HOLLOW (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Paku peluru ramset | BH | 0,3900 | 110,00 | 42,90 |
| 2 | Hollow 4x4 cm tbl 0.5 mm | BTG | 0,4590 | 42.350,00 | 19.438,65 |
| 3 | Hollow 2x4 cm tbl 0.5 mm | BTG | 0,4310 | 33.880,00 | 14.602,28 |
| 4 | Paku beton | KG | 0,0100 | 18.150,00 | 181,50 |
| 5 | Sekrup 6x1-1,5 | KG | 14,0000 | 242,00 | 3.388,00 |
| 6 | Calsiboard 120x240 cm 4 mm | LBR | 0,3640 | 80.300,00 | 29.229,20 |
| 7 | Sekrup gypsum | BH | 21,0000 | 220,00 | 4.620,00 |
| 8 | Textile tape | Roll | 0,0240 | 27.500,00 | 660,00 |
| 9 | Compound GRC | 20kg/zak | 0,0200 | 90.750,00 | 1.815,00 |
| 10 | Amplas | LBR | 0,1000 | 7.260,00 | 726,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2600 | 200.000,00 | 52.000,00 |
| 2 | Tukang alumunium | OH | 0,2600 | 150.000,00 | 39.000,00 |
| 3 | Tukang alumunium | OH | 0,0500 | 150.000,00 | 7.500,00 |
| 4 | Kepala tukang | OH | 0,0310 | 155.000,00 | 4.805,00 |
| 5 | Mandor | OH | 0,0130 | 165.000,00 | 2.145,00 |
| Jumlah | 180.153,53 | ||||
| Jasa 10% | 18.015,35 | ||||
| Total | 198.168,88 | ||||
G.4 — PENUTUP PLAFON GYPSUMBOARD 9 MM LENGKAP DGN RANGKA HOLLOW / TIAP 1 (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Paku peluru ramset | BH | 0,3900 | 110,00 | 42,90 |
| 2 | Hollow 4x4 cm tbl 0.5 mm | BTG | 0,4590 | 42.350,00 | 19.438,65 |
| 3 | Hollow 2x4 cm tbl 0.5 mm | BTG | 0,4310 | 33.880,00 | 14.602,28 |
| 4 | Paku beton | KG | 0,0100 | 18.150,00 | 181,50 |
| 5 | Sekrup 6x1-1,5 | KG | 14,0000 | 242,00 | 3.388,00 |
| 6 | Gypsumboard 120x240 cm 9 mm | LBR | 0,3640 | 81.400,00 | 29.629,60 |
| 7 | Sekrup gypsum | BH | 21,0000 | 220,00 | 4.620,00 |
| 8 | Textile tape | Roll | 0,0240 | 27.500,00 | 660,00 |
| 9 | Compound gypsum | 20kg/zak | 0,0200 | 83.490,00 | 1.669,80 |
| 10 | Amplas | LBR | 0,1000 | 7.260,00 | 726,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2600 | 200.000,00 | 52.000,00 |
| 2 | Tukang alumunium | OH | 0,2600 | 150.000,00 | 39.000,00 |
| 3 | Tukang gypsum | OH | 0,0500 | 150.000,00 | 7.500,00 |
| 4 | Kepala tukang | OH | 0,0310 | 155.000,00 | 4.805,00 |
| 5 | Mandor | OH | 0,0130 | 165.000,00 | 2.145,00 |
| Jumlah | 180.408,73 | ||||
| Jasa 10% | 18.040,87 | ||||
| Total | 198.449,60 | ||||
| KELOMPOK H |
H.1 — PASANG LISPLANK (2 X 20 X 2) CM KAYU KLS I (M')
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Papan Kls I | M³ | 0,0088 | 12.000.000,00 | 105.600,00 |
| 2 | Paku biasa 2"-5" | KG | 0,0600 | 21.780,00 | 1.306,80 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1000 | 200.000,00 | 20.000,00 |
| 2 | Tukang kayu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 144.281,80 | ||||
| Jasa 10% | 14.428,18 | ||||
| Total | 158.709,98 | ||||
| KELOMPOK I |
I.1 — BETON NON STRUKTUR 1PC : 3PS : 5KR - UNTUK RABATAN/ BETON TUMBUK (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 218,0000 | 1.540,00 | 335.720,00 |
| 2 | Pasir beton | M³ | 0,5200 | 220.000,00 | 114.400,00 |
| 3 | Batu pecah/split 1/2 | M³ | 0,8700 | 385.000,00 | 334.950,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,6500 | 200.000,00 | 330.000,00 |
| 2 | Tukang batu | OH | 0,2500 | 150.000,00 | 37.500,00 |
| 3 | Kepala tukang | OH | 0,0250 | 155.000,00 | 3.875,00 |
| 4 | Mandor | OH | 0,0800 | 165.000,00 | 13.200,00 |
| Jumlah | 1.169.645,00 | ||||
| Jasa 10% | 116.964,50 | ||||
| Total | 1.286.609,50 | ||||
I.2 — BETON STRUKTUR K-175 (1PC : 2,5PS : 3,5KR) (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 300,0000 | 1.540,00 | 462.000,00 |
| 2 | Pasir beton | M³ | 0,5260 | 220.000,00 | 115.720,00 |
| 3 | Batu pecah/split 1/2 | M³ | 0,7370 | 385.000,00 | 283.745,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,6500 | 200.000,00 | 330.000,00 |
| 2 | Tukang batu | OH | 0,2500 | 150.000,00 | 37.500,00 |
| 3 | Kepala tukang | OH | 0,0250 | 155.000,00 | 3.875,00 |
| 4 | Mandor | OH | 0,0800 | 165.000,00 | 13.200,00 |
| Jumlah | 1.246.040,00 | ||||
| Jasa 10% | 124.604,00 | ||||
| Total | 1.370.644,00 | ||||
I.3 — BETON STRUKTUR K-225 (1PC : 2PS : 3KR) (LS)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 350,0000 | 1.540,00 | 539.000,00 |
| 2 | Pasir beton | M³ | 0,4850 | 220.000,00 | 106.700,00 |
| 3 | Batu pecah/split 1/2 | M³ | 0,7270 | 385.000,00 | 279.895,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 2,0000 | 200.000,00 | 400.000,00 |
| 2 | Tukang batu | OH | 0,3500 | 150.000,00 | 52.500,00 |
| 3 | Kepala tukang | OH | 0,0350 | 155.000,00 | 5.425,00 |
| 4 | Mandor | OH | 0,1000 | 165.000,00 | 16.500,00 |
| Jumlah | 1.400.020,00 | ||||
| Jasa 10% | 140.002,00 | ||||
| Total | 1.540.022,00 | ||||
I.4 — BETON STRUKTUR K-275 (1PC : 1,5PS : 3KR) (LS)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 400,0000 | 1.540,00 | 616.000,00 |
| 2 | Pasir beton | M³ | 0,4170 | 220.000,00 | 91.740,00 |
| 3 | Batu pecah/split 1/2 | M³ | 0,8330 | 385.000,00 | 320.705,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 2,0000 | 200.000,00 | 400.000,00 |
| 2 | Tukang batu | OH | 0,3500 | 150.000,00 | 52.500,00 |
| 3 | Kepala tukang | OH | 0,0350 | 155.000,00 | 5.425,00 |
| 4 | Mandor | OH | 0,1000 | 165.000,00 | 16.500,00 |
| Jumlah | 1.502.870,00 | ||||
| Jasa 10% | 150.287,00 | ||||
| Total | 1.653.157,00 | ||||
I.5 — BETON STRUKTUR K-350 (1PC : 1,5PS : 2,75KR) (LS)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 425,0000 | 1.540,00 | 654.500,00 |
| 2 | Pasir beton | M³ | 0,4420 | 220.000,00 | 97.240,00 |
| 3 | Batu pecah/split 1/2 | M³ | 0,8110 | 385.000,00 | 312.235,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 2,0000 | 200.000,00 | 400.000,00 |
| 2 | Tukang batu | OH | 0,3500 | 150.000,00 | 52.500,00 |
| 3 | Kepala tukang | OH | 0,0350 | 155.000,00 | 5.425,00 |
| 4 | Mandor | OH | 0,1000 | 165.000,00 | 16.500,00 |
| Jumlah | 1.538.400,00 | ||||
| Jasa 10% | 153.840,00 | ||||
| Total | 1.692.240,00 | ||||
I.6 — BETON STRUKTUR K-400 (1PC : 1,5PS : 2,5KR) (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 450,0000 | 1.540,00 | 693.000,00 |
| 2 | Pasir beton | M³ | 0,4600 | 220.000,00 | 101.200,00 |
| 3 | Batu pecah/split 1/2 | M³ | 0,7900 | 385.000,00 | 304.150,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 2,0000 | 200.000,00 | 400.000,00 |
| 2 | Tukang batu | OH | 0,3500 | 150.000,00 | 52.500,00 |
| 3 | Kepala tukang | OH | 0,0350 | 155.000,00 | 5.425,00 |
| 4 | Mandor | OH | 0,1000 | 165.000,00 | 16.500,00 |
| Jumlah | 1.572.775,00 | ||||
| Jasa 10% | 157.277,50 | ||||
| Total | 1.730.052,50 | ||||
I.7 — BETON READY MIX K.300 (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Beton K-300 slump 12 | M³ | 1,1500 | 1.149.500,00 | 1.321.925,00 |
| 2 | Sewa Pompa Beton | M3 | 1,0000 | 25.250,00 | 25.250,00 |
| 3 | Ember Aduk | Bh | 0,0500 | 5.050,00 | 252,50 |
| 4 | Pacul Aduk | Bh | 0,0500 | 50.500,00 | 2.525,00 |
| 5 | Sekop | Bh | 0,0500 | 53.025,00 | 2.651,25 |
| 6 | Sewa Vibrator | Jam | 1,0000 | 39.969,93 | 39.969,93 |
| UPAH | |||||
| 1 | Pekerja | OH | 2,5000 | 200.000,00 | 500.000,00 |
| 2 | Tukang batu | OH | 0,4170 | 150.000,00 | 62.550,00 |
| 3 | Kepala tukang | OH | 0,0420 | 155.000,00 | 6.510,00 |
| 4 | Mandor | OH | 0,0080 | 165.000,00 | 1.320,00 |
| Jumlah | 1.962.953,68 | ||||
| Jasa 10% | 196.295,37 | ||||
| Total | 2.159.249,05 | ||||
I.8 — PEMBESIAN DENGAN BESI POLOS (KG)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi beton polos | KG | 1,0500 | 14.900,00 | 15.645,00 |
| 2 | Kawat beton | KG | 0,0150 | 30.250,00 | 453,75 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0070 | 200.000,00 | 1.400,00 |
| 2 | Kepala tukang | OH | 0,0007 | 155.000,00 | 108,50 |
| 3 | Mandor | OH | 0,0004 | 165.000,00 | 66,00 |
| 4 | Tukang besi | OH | 0,0070 | 150.000,00 | 1.050,00 |
| Jumlah | 18.723,25 | ||||
| Jasa 10% | 1.872,33 | ||||
| Total | 20.595,58 | ||||
I.9 — PEMBESIAN DENGAN BESI ULIR (KG)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi beton polos | KG | 1,0500 | 14.900,00 | 15.645,00 |
| 2 | Kawat beton | KG | 0,0150 | 30.250,00 | 453,75 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0070 | 200.000,00 | 1.400,00 |
| 2 | Tukang besi | OH | 0,0070 | 150.000,00 | 1.050,00 |
| 3 | Kepala tukang | OH | 0,0007 | 155.000,00 | 108,50 |
| 4 | Mandor | OH | 0,0004 | 165.000,00 | 66,00 |
| Jumlah | 18.723,25 | ||||
| Jasa 10% | 1.872,33 | ||||
| Total | 20.595,58 | ||||
I.10 — PASANG BEKISTING UNTUK PONDASI (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Balok Kls III | M³ | 0,0400 | 3.025.000,00 | 121.000,00 |
| 2 | Paku biasa 2"-5" | KG | 0,3000 | 21.780,00 | 6.534,00 |
| 3 | Minyak bekisting | LTR | 0,1000 | 7.260,00 | 726,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,5200 | 200.000,00 | 104.000,00 |
| 2 | Tukang kayu | OH | 0,2600 | 150.000,00 | 39.000,00 |
| 3 | Kepala tukang | OH | 0,0260 | 155.000,00 | 4.030,00 |
| 4 | Mandor | OH | 0,0260 | 165.000,00 | 4.290,00 |
| Jumlah | 279.580,00 | ||||
| Jasa 10% | 27.958,00 | ||||
| Total | 307.538,00 | ||||
I.11 — PASANG BEKISTING UNTUK SLOOF (OH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Balok Kls III | M³ | 0,0450 | 3.025.000,00 | 136.125,00 |
| 2 | Paku biasa 2"-5" | KG | 0,3000 | 21.780,00 | 6.534,00 |
| 3 | Minyak bekisting | LTR | 0,1000 | 7.260,00 | 726,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,5200 | 200.000,00 | 104.000,00 |
| 2 | Tukang kayu | OH | 0,2600 | 150.000,00 | 39.000,00 |
| 3 | Kepala tukang | OH | 0,0260 | 155.000,00 | 4.030,00 |
| 4 | Mandor | OH | 0,0260 | 165.000,00 | 4.290,00 |
| Jumlah | 294.705,00 | ||||
| Jasa 10% | 29.470,50 | ||||
| Total | 324.175,50 | ||||
I.12 — PASANG BEKISTING UNTUK KOLOM (OH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Balok Kls III | M³ | 0,0400 | 3.025.000,00 | 121.000,00 |
| 2 | Paku biasa 2"-5" | KG | 0,4000 | 21.780,00 | 8.712,00 |
| 3 | Minyak bekisting | LTR | 0,2000 | 7.260,00 | 1.452,00 |
| 4 | Kayu Balok Kls II | M³ | 0,0150 | 4.620.000,00 | 69.300,00 |
| 5 | Triplek 4x8 ft 9 mm | LBR | 0,3500 | 129.470,00 | 45.314,50 |
| 6 | Kayu Dolken | BTG | 2,0000 | 29.040,00 | 58.080,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,6600 | 200.000,00 | 132.000,00 |
| 2 | Tukang kayu | OH | 0,3300 | 150.000,00 | 49.500,00 |
| 3 | Kepala tukang | OH | 0,0330 | 155.000,00 | 5.115,00 |
| 4 | Mandor | OH | 0,0330 | 165.000,00 | 5.445,00 |
| Jumlah | 495.918,50 | ||||
| Jasa 10% | 49.591,85 | ||||
| Total | 545.510,35 | ||||
I.13 — PASANG BEKISTING UNTUK BALOK (OH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Balok Kls III | M³ | 0,0400 | 3.025.000,00 | 121.000,00 |
| 2 | Paku biasa 2"-5" | KG | 0,4000 | 21.780,00 | 8.712,00 |
| 3 | Minyak bekisting | LTR | 0,2000 | 7.260,00 | 1.452,00 |
| 4 | Kayu Balok Kls II | M³ | 0,0180 | 4.620.000,00 | 83.160,00 |
| 5 | Triplek 4x8 ft 9 mm | LBR | 0,3500 | 129.470,00 | 45.314,50 |
| 6 | Kayu Dolken | BTG | 2,0000 | 29.040,00 | 58.080,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,6600 | 200.000,00 | 132.000,00 |
| 2 | Tukang kayu | OH | 0,3300 | 150.000,00 | 49.500,00 |
| 3 | Kepala tukang | OH | 0,0330 | 155.000,00 | 5.115,00 |
| 4 | Mandor | OH | 0,0330 | 165.000,00 | 5.445,00 |
| Jumlah | 509.778,50 | ||||
| Jasa 10% | 50.977,85 | ||||
| Total | 560.756,35 | ||||
I.14 — PASANG BEKISTING UNTUK PELAT LANTAI (OH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Balok Kls III | M³ | 0,0400 | 3.025.000,00 | 121.000,00 |
| 2 | Paku biasa 2"-5" | KG | 0,4000 | 21.780,00 | 8.712,00 |
| 3 | Minyak bekisting | LTR | 0,2000 | 7.260,00 | 1.452,00 |
| 4 | Kayu Balok Kls II | M³ | 0,0150 | 4.620.000,00 | 69.300,00 |
| 5 | Triplek 4x8 ft 9 mm | LBR | 0,3500 | 129.470,00 | 45.314,50 |
| 6 | Kayu Dolken | BTG | 6,0000 | 29.040,00 | 174.240,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,6600 | 200.000,00 | 132.000,00 |
| 2 | Tukang kayu | OH | 0,3300 | 150.000,00 | 49.500,00 |
| 3 | Kepala tukang | OH | 0,0330 | 155.000,00 | 5.115,00 |
| 4 | Mandor | OH | 0,0330 | 165.000,00 | 5.445,00 |
| Jumlah | 612.078,50 | ||||
| Jasa 10% | 61.207,85 | ||||
| Total | 673.286,35 | ||||
I.15 — PASANG BEKISTING UNTUK DINDING ( M³ )
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kayu Balok Kls III | M³ | 0,0300 | 3.025.000,00 | 90.750,00 |
| 2 | Paku biasa 2"-5" | KG | 0,4000 | 21.780,00 | 8.712,00 |
| 3 | Minyak bekisting | LTR | 0,2000 | 7.260,00 | 1.452,00 |
| 4 | Kayu Balok Kls II | M³ | 0,0200 | 4.620.000,00 | 92.400,00 |
| 5 | Triplek 4x8 ft 9 mm | LBR | 0,3500 | 129.470,00 | 45.314,50 |
| 6 | Kayu Dolken | BTG | 6,0000 | 29.040,00 | 174.240,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 5,6500 | 200.000,00 | 1.130.000,00 |
| 2 | Tukang kayu | OH | 1,5600 | 150.000,00 | 234.000,00 |
| 3 | Kepala tukang | OH | 0,3230 | 155.000,00 | 50.065,00 |
| 4 | Mandor | OH | 0,2830 | 165.000,00 | 46.695,00 |
| Jumlah | 1.873.628,50 | ||||
| Jasa 10% | 187.362,85 | ||||
| Total | 2.060.991,35 | ||||
| KELOMPOK J |
J.1 — PASANG ATAP SENG GELOMBANG TIAP ( M2 )
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Seng gelombang 3x6 ft BJLS 20 (0,2 mm) | LBR | 0,7000 | 52.030,00 | 36.421,00 |
| 2 | Paku seng | KG | 0,0200 | 32.670,00 | 653,40 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1200 | 200.000,00 | 24.000,00 |
| 2 | Tukang kayu | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0060 | 165.000,00 | 990,00 |
| Jumlah | 71.994,40 | ||||
| Jasa 10% | 7.199,44 | ||||
| Total | 79.193,84 | ||||
J.2 — PASANG NOK SENG TIAP (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Seng plat 3x6 ft BJLS 20 (0,2 mm) | LBR | 0,3000 | 66.550,00 | 19.965,00 |
| 2 | Paku seng | KG | 0,0400 | 32.670,00 | 1.306,80 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1500 | 200.000,00 | 30.000,00 |
| 2 | Tukang kayu | OH | 0,0700 | 150.000,00 | 10.500,00 |
| 3 | Kepala tukang | OH | 0,0080 | 155.000,00 | 1.240,00 |
| 4 | Mandor | OH | 0,0060 | 165.000,00 | 990,00 |
| Jumlah | 64.001,80 | ||||
| Jasa 10% | 6.400,18 | ||||
| Total | 70.401,98 | ||||
J.3 — PASANG ATAP SPANDEK TIAP (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Spandek | Lbr | 1,0000 | 169.400,00 | 169.400,00 |
| 2 | Sekrup 6x1-1,5 | KG | 4,0000 | 242,00 | 968,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0800 | 200.000,00 | 16.000,00 |
| 2 | Tukang besi | OH | 0,0800 | 150.000,00 | 12.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0100 | 165.000,00 | 1.650,00 |
| Jumlah | 201.568,00 | ||||
| Jasa 10% | 20.156,80 | ||||
| Total | 221.724,80 | ||||
J.4 — PASANG NOK SPANDEK STANDAR TIAP 1 (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Nok zincalume | LBR | 1,1000 | 48.400,00 | 53.240,00 |
| 2 | Sekrup 6x1-1,5 | KG | 0,0400 | 242,00 | 9,68 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1500 | 200.000,00 | 30.000,00 |
| 2 | Tukang besi | OH | 0,0700 | 150.000,00 | 10.500,00 |
| 3 | Kepala tukang | OH | 0,0080 | 155.000,00 | 1.240,00 |
| 4 | Mandor | OH | 0,0060 | 165.000,00 | 990,00 |
| Jumlah | 95.979,68 | ||||
| Jasa 10% | 9.597,97 | ||||
| Total | 105.577,65 | ||||
J.5 — PASANG ATAP GENTENG METAL TIAP (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Genteng metal sakura | M2 | 1,0200 | 52.030,00 | 53.070,60 |
| 2 | Paku biasa 2"-5" | KG | 0,2000 | 21.780,00 | 4.356,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2000 | 200.000,00 | 40.000,00 |
| 2 | Tukang kayu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0010 | 165.000,00 | 165,00 |
| Jumlah | 114.141,60 | ||||
| Jasa 10% | 11.414,16 | ||||
| Total | 125.555,76 | ||||
J.6 — PASANG NOK GENTENG METAL TIAP 1 (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Nok stel rata Sakura | LBR | 1,1000 | 42.350,00 | 46.585,00 |
| 2 | Paku biasa 1/2"- 1" | KG | 0,0500 | 22.990,00 | 1.149,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2500 | 200.000,00 | 50.000,00 |
| 2 | Tukang kayu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0130 | 165.000,00 | 2.145,00 |
| Jumlah | 124.704,50 | ||||
| Jasa 10% | 12.470,45 | ||||
| Total | 137.174,95 | ||||
J.7 — PASANG TALANG DATAR (JURAI DALAM), SENG BJLS 28 (0,28 MM) TIAP 1 (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Seng plat 3x6 ft BJLS 20 (0,2 mm) | LBR | 0,5000 | 66.550,00 | 33.275,00 |
| 2 | Paku biasa 1/2"- 1" | KG | 0,0150 | 22.990,00 | 344,85 |
| 3 | Kayu Papan Kls II | M³ | 0,0190 | 4.620.000,00 | 87.780,00 |
| 4 | Cat meni besi | KG | 0,2500 | 22.990,00 | 5.747,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0400 | 200.000,00 | 8.000,00 |
| 2 | Tukang kayu | OH | 0,4000 | 150.000,00 | 60.000,00 |
| 3 | Kepala tukang | OH | 0,0250 | 155.000,00 | 3.875,00 |
| 4 | Mandor | OH | 0,0013 | 165.000,00 | 214,50 |
| Jumlah | 199.236,85 | ||||
| Jasa 10% | 19.923,69 | ||||
| Total | 219.160,54 | ||||
J.8 — PASANG ROOFMESH DAN ALUMUNIUM FOIL TIAP 1 (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Roofmesh 5 x 5 | M2 | 1,0500 | 20.000,00 | 21.000,00 |
| 2 | Allumunium foil | M² | 1,0500 | 26.000,00 | 27.300,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1500 | 200.000,00 | 30.000,00 |
| 2 | Tukang besi | OH | 0,0500 | 150.000,00 | 7.500,00 |
| 3 | Kepala tukang | OH | 0,0050 | 155.000,00 | 775,00 |
| 4 | Mandor | OH | 0,0080 | 165.000,00 | 1.320,00 |
| Jumlah | 87.895,00 | ||||
| Jasa 10% | 8.789,50 | ||||
| Total | 96.684,50 | ||||
| KELOMPOK K |
K.1 — MEMASANG 1 BUAH KLOSET JONGKOK (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kloset jongkok standart | BH | 1,0000 | 2.530.000,00 | 2.530.000,00 |
| 2 | Semen portland | KG | 6,0000 | 1.540,00 | 9.240,00 |
| 3 | Pasir pasang | M³ | 0,0100 | 400.000,00 | 4.000,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,0000 | 200.000,00 | 200.000,00 |
| 2 | Tukang batu | OH | 1,5000 | 150.000,00 | 225.000,00 |
| 3 | Kepala tukang | OH | 0,1500 | 155.000,00 | 23.250,00 |
| 4 | Mandor | OH | 0,1600 | 165.000,00 | 26.400,00 |
| Jumlah | 3.017.890,00 | ||||
| Jasa 10% | 301.789,00 | ||||
| Total | 3.319.679,00 | ||||
K.2 — MEMASANG 1 BUAH KLOSET DUDUK (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kloset duduk standart | BH | 1,0000 | 2.530.000,00 | 2.530.000,00 |
| 2 | Perlengkapan (6% harga kloset duduk) | % | 0,0600 | 2.530.000,00 | 151.800,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 3,3000 | 200.000,00 | 660.000,00 |
| 2 | Tukang batu | OH | 1,1000 | 150.000,00 | 165.000,00 |
| 3 | Kepala tukang | OH | 0,0010 | 155.000,00 | 155,00 |
| 4 | Mandor | OH | 0,1600 | 165.000,00 | 26.400,00 |
| Jumlah | 3.533.355,00 | ||||
| Jasa 10% | 353.335,50 | ||||
| Total | 3.886.690,50 | ||||
K.3 — MEMASANG 1 BUAH URINOIR (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Urinoir | BH | 1,0000 | 2.000.000,00 | 2.000.000,00 |
| 2 | Perlengkapan (30% harga urinoir) | % | 0,3000 | 2.000.000,00 | 600.000,00 |
| 3 | Semen portland | KG | 6,0000 | 1.540,00 | 9.240,00 |
| 4 | Pasir pasang | M³ | 0,0100 | 400.000,00 | 4.000,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,0000 | 200.000,00 | 200.000,00 |
| 2 | Tukang batu | OH | 1,0000 | 150.000,00 | 150.000,00 |
| 3 | Kepala tukang | OH | 0,1000 | 155.000,00 | 15.500,00 |
| 4 | Mandor | OH | 0,1000 | 165.000,00 | 16.500,00 |
| Jumlah | 2.995.240,00 | ||||
| Jasa 10% | 299.524,00 | ||||
| Total | 3.294.764,00 | ||||
K.4 — MEMASANG 1 BUAH WASTAFEL (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Wastafel | BH | 1,0000 | 308.550,00 | 308.550,00 |
| 2 | Perlengkapan (12% harga wastafel) | % | 0,1200 | 308.550,00 | 37.026,00 |
| 3 | Semen portland | KG | 6,0000 | 1.540,00 | 9.240,00 |
| 4 | Pasir pasang | M³ | 0,0100 | 400.000,00 | 4.000,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,2000 | 200.000,00 | 240.000,00 |
| 2 | Tukang batu | OH | 1,4500 | 150.000,00 | 217.500,00 |
| 3 | Kepala tukang | OH | 0,1500 | 155.000,00 | 23.250,00 |
| 4 | Mandor | OH | 0,1000 | 165.000,00 | 16.500,00 |
| Jumlah | 856.066,00 | ||||
| Jasa 10% | 85.606,60 | ||||
| Total | 941.672,60 | ||||
K.5 — MEMASANG PIPA PVC TIPE AW DIA 1/2" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 1/2" AW | M' | 1,2000 | 6.600,00 | 7.920,00 |
| 2 | Perlengkapan (35% harga pipa PVC dia 1/2") | % | 0,3500 | 6.600,00 | 2.310,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0360 | 200.000,00 | 7.200,00 |
| 2 | Tukang pipa | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0018 | 165.000,00 | 297,00 |
| Jumlah | 27.657,00 | ||||
| Jasa 10% | 2.765,70 | ||||
| Total | 30.422,70 | ||||
K.6 — MEMASANG PIPA PVC TIPE AW DIA 3/4" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 3/4" AW | M' | 1,2000 | 8.400,00 | 10.080,00 |
| 2 | Perlengkapan (35% harga pipa AW 3/4") | % | 0,3500 | 8.400,00 | 2.940,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0360 | 200.000,00 | 7.200,00 |
| 2 | Tukang pipa | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0018 | 165.000,00 | 297,00 |
| Jumlah | 30.447,00 | ||||
| Jasa 10% | 3.044,70 | ||||
| Total | 33.491,70 | ||||
K.7 — MEMASANG PIPA PVC TIPE AW DIA 1" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 1" AW | M' | 1,2000 | 10.890,00 | 13.068,00 |
| 2 | Perlengkapan (35% harga pipa AW 1") | % | 0,3500 | 10.890,00 | 3.811,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0360 | 200.000,00 | 7.200,00 |
| 2 | Tukang pipa | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0018 | 165.000,00 | 297,00 |
| Jumlah | 34.306,50 | ||||
| Jasa 10% | 3.430,65 | ||||
| Total | 37.737,15 | ||||
K.8 — MEMASANG PIPA PVC TIPE AW DIA 1,5" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 1 ½" AW | M' | 1,2000 | 19.360,00 | 23.232,00 |
| 2 | Perlengkapan (35% harga pipa AW 1 1/2") | % | 0,3500 | 19.360,00 | 6.776,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0360 | 200.000,00 | 7.200,00 |
| 2 | Tukang pipa | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0018 | 165.000,00 | 297,00 |
| Jumlah | 47.435,00 | ||||
| Jasa 10% | 4.743,50 | ||||
| Total | 52.178,50 | ||||
K.9 — MEMASANG PIPA PVC TIPE AW DIA 2" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 2" AW | M' | 1,2000 | 24.200,00 | 29.040,00 |
| 2 | Perlengkapan (35% harga pipa AW 2") | % | 0,3500 | 24.200,00 | 8.470,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0540 | 200.000,00 | 10.800,00 |
| 2 | Tukang pipa | OH | 0,0900 | 150.000,00 | 13.500,00 |
| 3 | Kepala tukang | OH | 0,0090 | 155.000,00 | 1.395,00 |
| 4 | Mandor | OH | 0,0027 | 165.000,00 | 445,50 |
| Jumlah | 63.650,50 | ||||
| Jasa 10% | 6.365,05 | ||||
| Total | 70.015,55 | ||||
K.10 — MEMASANG PIPA PVC TIPE AW DIA 2 ½" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 2 ½" AW | M' | 1,2000 | 25.410,00 | 30.492,00 |
| 2 | Perlengkapan (35% harga pipa AW 2 1/2") | % | 0,3500 | 25.410,00 | 8.893,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0360 | 200.000,00 | 7.200,00 |
| 2 | Tukang pipa | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0002 | 165.000,00 | 29,70 |
| Jumlah | 56.545,20 | ||||
| Jasa 10% | 5.654,52 | ||||
| Total | 62.199,72 | ||||
K.11 — MEMASANG PIPA PVC TIPE AW DIA 3" CM (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 3" AW | M' | 1,2000 | 45.980,00 | 55.176,00 |
| 2 | Perlengkapan (35% harga pipa PVC tipe AW 3") | % | 0,3500 | 45.980,00 | 16.093,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0810 | 200.000,00 | 16.200,00 |
| 2 | Tukang pipa | OH | 0,1350 | 150.000,00 | 20.250,00 |
| 3 | Kepala tukang | OH | 0,0135 | 155.000,00 | 2.092,50 |
| 4 | Mandor | OH | 0,0041 | 165.000,00 | 676,50 |
| Jumlah | 110.488,00 | ||||
| Jasa 10% | 11.048,80 | ||||
| Total | 121.536,80 | ||||
K.12 — MEMASANG PIPA PVC TIPE AW DIA 4" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 4" AW | M' | 1,2000 | 73.810,00 | 88.572,00 |
| 2 | Perlengkapan (35% harga pipa PVC tipe AW 4") | % | 0,3500 | 73.810,00 | 25.833,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0810 | 200.000,00 | 16.200,00 |
| 2 | Tukang pipa | OH | 0,1350 | 150.000,00 | 20.250,00 |
| 3 | Kepala tukang | OH | 0,0135 | 155.000,00 | 2.092,50 |
| 4 | Mandor | OH | 0,0041 | 165.000,00 | 676,50 |
| Jumlah | 153.624,50 | ||||
| Jasa 10% | 15.362,45 | ||||
| Total | 168.986,95 | ||||
K.13 — MEMASANG PIPA PVC TIPE D DIA 4" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 4" D | M' | 1,2000 | 53.240,00 | 63.888,00 |
| 2 | Perlengkapan (35% harga pipa PVC tipe D dia 4") | M | 0,3500 | 53.240,00 | 18.634,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0810 | 200.000,00 | 16.200,00 |
| 2 | Tukang pipa | OH | 0,1350 | 150.000,00 | 20.250,00 |
| 3 | Kepala tukang | OH | 0,0135 | 155.000,00 | 2.092,50 |
| 4 | Mandor | OH | 0,0041 | 165.000,00 | 676,50 |
| Jumlah | 121.741,00 | ||||
| Jasa 10% | 12.174,10 | ||||
| Total | 133.915,10 | ||||
K.14 — MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS STEEL (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Bak cuci stainless steel | BH | 1,0000 | 288.000,00 | 288.000,00 |
| 2 | Water drain + asesoris | BH | 1,0000 | 114.950,00 | 114.950,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0300 | 200.000,00 | 6.000,00 |
| 2 | Tukang batu | OH | 0,3000 | 150.000,00 | 45.000,00 |
| 3 | Kepala tukang | OH | 0,0300 | 155.000,00 | 4.650,00 |
| 4 | Mandor | OH | 0,0015 | 165.000,00 | 247,50 |
| Jumlah | 458.847,50 | ||||
| Jasa 10% | 45.884,75 | ||||
| Total | 504.732,25 | ||||
K.15 — MEMASANG 1 BUAH KRAN 1/2" (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kran air | BH | 1,0000 | 66.700,00 | 66.700,00 |
| 2 | Seal tape | BH | 0,0250 | 4.235,00 | 105,88 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0100 | 200.000,00 | 2.000,00 |
| 2 | Tukang pipa | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 86.180,88 | ||||
| Jasa 10% | 8.618,09 | ||||
| Total | 94.798,96 | ||||
K.16 — MEMASANG 1 BUAH KRAN SHOWER (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kran Shower | BH | 1,0000 | 911.130,00 | 911.130,00 |
| 2 | Seal tape | BH | 0,0250 | 4.235,00 | 105,88 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0100 | 200.000,00 | 2.000,00 |
| 2 | Tukang pipa | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 930.610,88 | ||||
| Jasa 10% | 93.061,09 | ||||
| Total | 1.023.671,96 | ||||
K.17 — MEMASANG 1 BUAH JET WASHER (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kran air Jet Washer | BH | 1,0000 | 181.500,00 | 181.500,00 |
| 2 | Seal tape | BH | 0,0250 | 4.235,00 | 105,88 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0100 | 200.000,00 | 2.000,00 |
| 2 | Tukang pipa | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 200.980,88 | ||||
| Jasa 10% | 20.098,09 | ||||
| Total | 221.078,96 | ||||
K.18 — MEMASANG 1 FLOOR DRAIN SEDERHANA (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Floor drain | BH | 1,0000 | 24.200,00 | 24.200,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0100 | 200.000,00 | 2.000,00 |
| 2 | Tukang batu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 43.575,00 | ||||
| Jasa 10% | 4.357,50 | ||||
| Total | 47.932,50 | ||||
K.19 — MEMBUAT 1 UNIT SUMUR AIR TANAH BOR MANUAL DALAM 10 M' + POMPA AIR LISTRIK (UNIT)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Pipa PVC dia 3/4" AW | M' | 14,0000 | 8.400,00 | 117.600,00 |
| 2 | Perlengkapan (35% harga pipa AW 3/4") | % | 0,3500 | 8.400,00 | 2.940,00 |
| 3 | Pipa PVC dia 4" D | M' | 12,0000 | 53.240,00 | 638.880,00 |
| 4 | Perlengkapan (35% harga pipa PVC tipe D dia 4") | M | 0,3500 | 53.240,00 | 18.634,00 |
| 5 | Pompa air listrik Shimizu 125 W | UNIT | 1,0000 | 715.000,00 | 715.000,00 |
| 6 | Perlengkapan (35% pompa) | % | 0,3500 | 715.000,00 | 250.250,00 |
| 7 | Galian Sumur | M | 10,0000 | 100.000,00 | 1.000.000,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 3,1620 | 200.000,00 | 632.400,00 |
| 2 | Tukang pipa | OH | 2,3200 | 150.000,00 | 348.000,00 |
| 3 | Kepala tukang | OH | 0,2320 | 155.000,00 | 35.960,00 |
| 4 | Mandor | OH | 0,1581 | 165.000,00 | 26.086,50 |
| Jumlah | 3.785.750,50 | ||||
| Jasa 10% | 378.575,05 | ||||
| Total | 4.164.325,55 | ||||
K.20 — MEMBUAT TANKI SEPTIK / RESAPAN KAPASITAS TIAP 1 (20)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Bata merah | BH | 385,0000 | 990,00 | 381.150,00 |
| 2 | Semen portland | KG | 162,2900 | 1.540,00 | 249.926,60 |
| 3 | Pasir pasang | M³ | 0,3140 | 400.000,00 | 125.600,00 |
| 4 | Batu pecah/split 1/2 | M³ | 0,1070 | 385.000,00 | 41.195,00 |
| 5 | Besi beton polos | KG | 16,5940 | 14.900,00 | 247.250,60 |
| 6 | Kawat beton | KG | 0,2370 | 30.250,00 | 7.169,25 |
| 7 | Pasir beton | M³ | 0,0720 | 220.000,00 | 15.840,00 |
| 8 | Pasir urug | M | 0,0740 | 121.000,00 | 8.954,00 |
| 9 | Kayu Balok Kls II | M³ | 0,0230 | 4.620.000,00 | 106.260,00 |
| 10 | Triplek 4x8 ft 9 mm | LBR | 0,4260 | 129.470,00 | 55.154,22 |
| 11 | Paku biasa 2"-5" | KG | 0,4900 | 21.780,00 | 10.672,20 |
| 12 | Pipa PVC dia 2" D | M' | 1,6000 | 14.520,00 | 23.232,00 |
| 13 | Pipa PVC dia 4" D | M' | 4,0000 | 53.240,00 | 212.960,00 |
| 14 | Perlengkapan (35% harga pipa PVC tipe D dia 4") | M | 0,3500 | 53.240,00 | 18.634,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 4,6040 | 200.000,00 | 920.800,00 |
| 2 | Tukang batu | OH | 1,8560 | 150.000,00 | 278.400,00 |
| 3 | Tukang pipa | OH | 0,2670 | 150.000,00 | 40.050,00 |
| 4 | Kepala tukang | OH | 0,2130 | 155.000,00 | 33.015,00 |
| 5 | Mandor | OH | 0,2570 | 165.000,00 | 42.405,00 |
| Jumlah | 2.818.667,87 | ||||
| Jasa 10% | 281.866,79 | ||||
| Total | 3.100.534,66 | ||||
| KELOMPOK L |
L.1 — PASANG 1 BUAH KUNCI TANAM (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kunci Tanam Biasa | BH | 1,0000 | 200.000,00 | 200.000,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0600 | 200.000,00 | 12.000,00 |
| 2 | Tukang kayu | OH | 0,6000 | 150.000,00 | 90.000,00 |
| 3 | Kepala tukang | OH | 0,0600 | 155.000,00 | 9.300,00 |
| 4 | Mandor | OH | 0,0030 | 165.000,00 | 495,00 |
| Jumlah | 311.795,00 | ||||
| Jasa 10% | 31.179,50 | ||||
| Total | 342.974,50 | ||||
L.2 — PASANG 1 BUAH ENGSEL PINTU (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Engsel Pintu Kuningan/Stainless | BH | 1,0000 | 47.190,00 | 47.190,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0150 | 200.000,00 | 3.000,00 |
| 2 | Tukang kayu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0008 | 165.000,00 | 123,75 |
| Jumlah | 75.138,75 | ||||
| Jasa 10% | 7.513,88 | ||||
| Total | 82.652,63 | ||||
L.3 — PASANG 1 BUAH ENGSEL JENDELA WINDOW CASEMENT (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Window Casement | BH | 1,0000 | 82.500,00 | 82.500,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0150 | 200.000,00 | 3.000,00 |
| 2 | Tukang kayu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0008 | 165.000,00 | 123,75 |
| Jumlah | 110.448,75 | ||||
| Jasa 10% | 11.044,88 | ||||
| Total | 121.493,63 | ||||
L.4 — PASANG 1 BUAH KAIT ANGIN/ RAM BUNCIS (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kait Angin/Rambuncis | Bh | 1,0000 | 49.500,00 | 49.500,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0150 | 200.000,00 | 3.000,00 |
| 2 | Tukang kayu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0008 | 165.000,00 | 123,75 |
| Jumlah | 77.448,75 | ||||
| Jasa 10% | 7.744,88 | ||||
| Total | 85.193,63 | ||||
L.5 — PASANG 1 BUAH ENGSEL JENDELA (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Engsel Jendela Kuningan/Stainless | BH | 1,0000 | 17.500,00 | 17.500,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0150 | 200.000,00 | 3.000,00 |
| 2 | Tukang kayu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0008 | 165.000,00 | 123,75 |
| Jumlah | 45.448,75 | ||||
| Jasa 10% | 4.544,88 | ||||
| Total | 49.993,63 | ||||
L.6 — PASANG 1 BUAH KAIT ANGIN (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kait Angin | BH | 1,0000 | 7.500,00 | 7.500,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0150 | 200.000,00 | 3.000,00 |
| 2 | Tukang kayu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0008 | 165.000,00 | 123,75 |
| Jumlah | 35.448,75 | ||||
| Jasa 10% | 3.544,88 | ||||
| Total | 38.993,63 | ||||
L.7 — PASANG 1 BUAH GERENDEL (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Gerendel Jendela | BH | 1,0000 | 18.150,00 | 18.150,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0200 | 200.000,00 | 4.000,00 |
| 2 | Tukang kayu | OH | 0,2000 | 150.000,00 | 30.000,00 |
| 3 | Kepala tukang | OH | 0,0200 | 155.000,00 | 3.100,00 |
| 4 | Mandor | OH | 0,0010 | 165.000,00 | 165,00 |
| Jumlah | 55.415,00 | ||||
| Jasa 10% | 5.541,50 | ||||
| Total | 60.956,50 | ||||
L.8 — PASANG KACA TEBAL 5 MM TIAP 1 (BH)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kaca 5 mm | M² | 1,1000 | 159.500,00 | 175.450,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0150 | 200.000,00 | 3.000,00 |
| 2 | Tukang kayu | OH | 0,1500 | 150.000,00 | 22.500,00 |
| 3 | Kepala tukang | OH | 0,0150 | 155.000,00 | 2.325,00 |
| 4 | Mandor | OH | 0,0008 | 165.000,00 | 123,75 |
| Jumlah | 203.398,75 | ||||
| Jasa 10% | 20.339,88 | ||||
| Total | 223.738,63 | ||||
| KELOMPOK M |
M.1 — PEKERJAAN 1 KG RANGKA KUDA KUDA BAJA IWF (KG)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi IWF 150 x 75 x 5 x 7 mm | KG | 1,1500 | 14.520,00 | 16.698,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0600 | 200.000,00 | 12.000,00 |
| 2 | Tukang las | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0030 | 165.000,00 | 495,00 |
| Jumlah | 39.123,00 | ||||
| Jasa 10% | 3.912,30 | ||||
| Total | 43.035,30 | ||||
M.2 — PEKERJAAN BESI L (KG)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi Siku | KG | 1,1500 | 13.310,00 | 15.306,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0600 | 200.000,00 | 12.000,00 |
| 2 | Tukang las | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0030 | 165.000,00 | 495,00 |
| Jumlah | 37.731,50 | ||||
| Jasa 10% | 3.773,15 | ||||
| Total | 41.504,65 | ||||
M.3 — PEKERJAAN 1 KG LISPLANK CANAL C (KG)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi kanal C 150x50x20x3.2 mm | KG | 1,1500 | 14.520,00 | 16.698,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0600 | 200.000,00 | 12.000,00 |
| 2 | Tukang las | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0030 | 165.000,00 | 495,00 |
| Jumlah | 39.123,00 | ||||
| Jasa 10% | 3.912,30 | ||||
| Total | 43.035,30 | ||||
M.4 — PEKERJAAN 1 KG GORDING CANAL C (KG)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi Kanal C 125x50x20x3.2 mm | KG | 1,1500 | 14.520,00 | 16.698,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0600 | 200.000,00 | 12.000,00 |
| 2 | Tukang las | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0030 | 165.000,00 | 495,00 |
| Jumlah | 39.123,00 | ||||
| Jasa 10% | 3.912,30 | ||||
| Total | 43.035,30 | ||||
M.5 — MENGERJAKAN 100 KG PEKERJAAN PERAKITAN (KG)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Solar | LTR | 1,0000 | 9.680,00 | 9.680,00 |
| 2 | Minyak Pelumas | LTR | 0,1000 | 36.300,00 | 3.630,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1000 | 200.000,00 | 20.000,00 |
| 2 | Tukang besi | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0010 | 155.000,00 | 155,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| 5 | Sewa mesin las | HR | 0,0080 | 363.000,00 | 2.904,00 |
| Jumlah | 52.194,00 | ||||
| Jasa 10% | 5.219,40 | ||||
| Total | 57.413,40 | ||||
M.6 — MENGERJAKAN 1 CM PENGELASAN DENGAN LAS LISTRIK (CM)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kawat Las listrik | KG | 0,0400 | 30.250,00 | 1.210,00 |
| 2 | Solar | LTR | 0,0300 | 9.680,00 | 290,40 |
| 3 | Minyak Pelumas | LTR | 0,0040 | 36.300,00 | 145,20 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0040 | 200.000,00 | 800,00 |
| 2 | Tukang las | OH | 0,0020 | 150.000,00 | 300,00 |
| 3 | Kepala tukang | OH | 0,0002 | 155.000,00 | 31,00 |
| 4 | Mandor | OH | 0,0002 | 165.000,00 | 33,00 |
| 5 | Sewa mesin las | HR | 0,0021 | 363.000,00 | 762,30 |
| Jumlah | 3.571,90 | ||||
| Jasa 10% | 357,19 | ||||
| Total | 3.929,09 | ||||
M.7 — PASANG KUSEN BAJA KANAL UNP 100 X 50 X 6 MM TIAP M' (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi Baja Kanal UNP | KG | 10,6000 | 11.150,00 | 118.190,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0600 | 200.000,00 | 12.000,00 |
| 2 | Tukang las | OH | 0,0600 | 150.000,00 | 9.000,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0030 | 165.000,00 | 495,00 |
| Jumlah | 140.615,00 | ||||
| Jasa 10% | 14.061,50 | ||||
| Total | 154.676,50 | ||||
M.8 — PASANG PINTU BESI PLAT BAJA TEBAL 2 MM RANGKAP, RANGKA BAJA SIKU (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi Siku | KG | 15,0000 | 13.310,00 | 199.650,00 |
| 2 | Plat 12 mm | KG | 32,8000 | 13.310,00 | 436.568,00 |
| 3 | Kawat Las listrik | KG | 0,0500 | 30.250,00 | 1.512,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,0500 | 200.000,00 | 210.000,00 |
| 2 | Tukang besi | OH | 1,0500 | 150.000,00 | 157.500,00 |
| 3 | Kepala tukang | OH | 0,1050 | 155.000,00 | 16.275,00 |
| 4 | Mandor | OH | 0,0520 | 165.000,00 | 8.580,00 |
| Jumlah | 1.030.085,50 | ||||
| Jasa 10% | 103.008,55 | ||||
| Total | 1.133.094,05 | ||||
M.9 — PASANG PINTU BESI PLAT BAJA TEBAL 3 MM RANGKA BAJA SIKU (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi Siku | KG | 15,0000 | 13.310,00 | 199.650,00 |
| 2 | Besi Plat 3 mm | KG | 26,7361 | 13.310,00 | 355.857,49 |
| 3 | Kawat Las listrik | KG | 0,0500 | 30.250,00 | 1.512,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,0500 | 200.000,00 | 210.000,00 |
| 2 | Tukang besi | OH | 1,0500 | 150.000,00 | 157.500,00 |
| 3 | Kepala tukang | OH | 0,1050 | 155.000,00 | 16.275,00 |
| 4 | Mandor | OH | 0,0520 | 165.000,00 | 8.580,00 |
| Jumlah | 949.374,99 | ||||
| Jasa 10% | 94.937,50 | ||||
| Total | 1.044.312,49 | ||||
M.10 — MENGERJAKAN 1 CM PENGELASAN DENGAN LAS LISTRIK (CM)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kawat Las listrik | KG | 0,0400 | 30.250,00 | 1.210,00 |
| 2 | Solar | LTR | 0,0300 | 9.680,00 | 290,40 |
| 3 | Minyak Pelumas | LTR | 0,0040 | 36.300,00 | 145,20 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0040 | 200.000,00 | 800,00 |
| 2 | Tukang batu | OH | 0,0020 | 150.000,00 | 300,00 |
| 3 | Kepala tukang | OH | 0,0002 | 155.000,00 | 31,00 |
| 4 | Mandor | OH | 0,0002 | 165.000,00 | 33,00 |
| 5 | Sewa mesin las | HR | 0,0021 | 363.000,00 | 762,30 |
| Jumlah | 3.571,90 | ||||
| Jasa 10% | 357,19 | ||||
| Total | 3.929,09 | ||||
M.11 — PASANG PINTU BESI PLAT BAJA TEBAL 2 MM RANGKAP, RANGKA BAJA SIKU (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi Siku | KG | 15,0000 | 13.310,00 | 199.650,00 |
| 2 | Plat 12 mm | KG | 32,8000 | 13.310,00 | 436.568,00 |
| 3 | Kawat Las listrik | KG | 0,0500 | 30.250,00 | 1.512,50 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,0500 | 200.000,00 | 210.000,00 |
| 2 | Tukang besi | OH | 1,0500 | 150.000,00 | 157.500,00 |
| 3 | Kepala tukang | OH | 0,1050 | 155.000,00 | 16.275,00 |
| 4 | Mandor | OH | 0,0520 | 165.000,00 | 8.580,00 |
| Jumlah | 1.030.085,50 | ||||
| Jasa 10% | 103.008,55 | ||||
| Total | 1.133.094,05 | ||||
M.12 — PEKERJAAN PASANG TERALI BESI (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Besi Plat 10 mm.4'.8' | KG | 5,1460 | 15.730,00 | 80.946,58 |
| 2 | Pengelasan | Cm | 27,0800 | 3.300,00 | 89.364,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 1,6700 | 200.000,00 | 334.000,00 |
| 2 | Tukang las | OH | 1,6700 | 150.000,00 | 250.500,00 |
| 3 | Kepala tukang | OH | 0,1670 | 155.000,00 | 25.885,00 |
| 4 | Mandor | OH | 0,0830 | 165.000,00 | 13.695,00 |
| Jumlah | 794.390,58 | ||||
| Jasa 10% | 79.439,06 | ||||
| Total | 873.829,64 | ||||
M.13 — PASANG KAWAT HARMONIKA (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kawat Harmonika | M2 | 1,1000 | 121.000,00 | 133.100,00 |
| 2 | Paku biasa 1/2"- 1" | KG | 0,0200 | 22.990,00 | 459,80 |
| 3 | Kayu Balok Kls II | M³ | 0,0018 | 4.620.000,00 | 8.316,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1000 | 200.000,00 | 20.000,00 |
| 2 | Tukang kayu | OH | 0,1000 | 150.000,00 | 15.000,00 |
| 3 | Kepala tukang | OH | 0,0100 | 155.000,00 | 1.550,00 |
| 4 | Mandor | OH | 0,0005 | 165.000,00 | 82,50 |
| Jumlah | 178.508,30 | ||||
| Jasa 10% | 17.850,83 | ||||
| Total | 196.359,13 | ||||
M.14 — MEMASANG PINTU/JENDELA/BV KACA RANGKA ALLUMUNIUM (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Profil Allumunium Kusen 4'' | M' | 4,4000 | 147.400,00 | 648.560,00 |
| 2 | Kaca 5 mm | M² | 1,0500 | 159.500,00 | 167.475,00 |
| 3 | Sealant | BH | 0,2700 | 43.560,00 | 11.761,20 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0850 | 200.000,00 | 17.000,00 |
| 2 | Tukang alumunium | OH | 0,0850 | 150.000,00 | 12.750,00 |
| 3 | Kepala tukang | OH | 0,0080 | 155.000,00 | 1.240,00 |
| 4 | Mandor | OH | 0,0040 | 165.000,00 | 660,00 |
| Jumlah | 859.446,20 | ||||
| Jasa 10% | 85.944,62 | ||||
| Total | 945.390,82 | ||||
M.15 — PASANG KUSEN PINTU ALUMINIUM (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Profil Allumunium Kusen 4'' | M' | 1,1000 | 147.400,00 | 162.140,00 |
| 2 | Skrup fixer | BH | 2,0000 | 96.800,00 | 193.600,00 |
| 3 | Sealant | BH | 0,0600 | 43.560,00 | 2.613,60 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0430 | 200.000,00 | 8.600,00 |
| 2 | Tukang alumunium | OH | 0,0430 | 150.000,00 | 6.450,00 |
| 3 | Kepala tukang | OH | 0,0043 | 155.000,00 | 666,50 |
| 4 | Mandor | OH | 0,0021 | 165.000,00 | 346,50 |
| Jumlah | 374.416,60 | ||||
| Jasa 10% | 37.441,66 | ||||
| Total | 411.858,26 | ||||
M.16 — PEKERJAAN PINTU TRALI BESI TIAP (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Engsel Pintu Kuningan/Stainless | BH | 3,0000 | 47.190,00 | 141.570,00 |
| 2 | Besi 16 mm | Kg | 31,6000 | 14.864,00 | 469.702,40 |
| 3 | Besi Siku | KG | 31,8750 | 13.310,00 | 424.256,25 |
| 4 | Kawat Las listrik | KG | 0,4000 | 30.250,00 | 12.100,00 |
| 5 | Sewa mesin las | HR | 0,4000 | 363.000,00 | 145.200,00 |
| 6 | Solar | LTR | 0,3000 | 9.680,00 | 2.904,00 |
| 7 | Minyak Pelumas | LTR | 0,0400 | 36.300,00 | 1.452,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0750 | 200.000,00 | 15.000,00 |
| 2 | Tukang las | OH | 0,0300 | 150.000,00 | 4.500,00 |
| 3 | Tukang besi | OH | 0,0800 | 150.000,00 | 12.000,00 |
| 4 | Kepala tukang | OH | 0,0080 | 155.000,00 | 1.240,00 |
| 5 | Mandor | OH | 0,0150 | 165.000,00 | 2.475,00 |
| Jumlah | 1.232.399,65 | ||||
| Jasa 10% | 123.239,97 | ||||
| Total | 1.355.639,62 | ||||
M.17 — PEMASANGAN ALCOPAN (M2)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| Data AHSP belum tersedia | |||||
| Jumlah | 0,00 | ||||
| Jasa 10% | 0,00 | ||||
| Total | 0,00 | ||||
| KELOMPOK N |
N.1 — PASANG LANTAI KERAMIK UKURAN 40 X 40 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Ubin keramik 40 x 40 cm KW 1 Asia Tile | BH | 6,6300 | 13.108.337,00 | 86.908.274,31 |
| 2 | Semen portland | KG | 9,8000 | 1.540,00 | 15.092,00 |
| 3 | Pasir pasang | M³ | 0,0450 | 400.000,00 | 18.000,00 |
| 4 | Semen warna/putih | KG | 1,3000 | 217.800,00 | 283.140,00 |
| Jumlah | 87.224.506,31 | ||||
| Jasa 10% | 8.722.450,63 | ||||
| Total | 95.946.956,94 | ||||
N.2 — PASANG LANTAI KERAMIK UKURAN 60 X 60 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | lantai keramik 60 x 60 cm | BH | 2,7778 | 43.000,00 | 119.444,11 |
| 2 | Semen portland | KG | 9,8000 | 1.540,00 | 15.092,00 |
| 3 | Pasir pasang | M³ | 0,0450 | 400.000,00 | 18.000,00 |
| 4 | Semen warna/putih | KG | 1,3000 | 217.800,00 | 283.140,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2500 | 200.000,00 | 50.000,00 |
| 2 | Tukang batu | OH | 0,1250 | 150.000,00 | 18.750,00 |
| 3 | Kepala tukang | OH | 0,0130 | 155.000,00 | 2.015,00 |
| 4 | Mandor | OH | 0,0130 | 165.000,00 | 2.145,00 |
| Jumlah | 508.586,11 | ||||
| Jasa 10% | 50.858,61 | ||||
| Total | 559.444,72 | ||||
N.3 — PASANG LANTAI KERAMIK UKURAN 40 X 40 CM KASAR (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | lantai keramik 40 x 40 cm kasar | BH | 6,6300 | 17.141.663,00 | 113.649.225,69 |
| 2 | Semen portland | KG | 9,8000 | 1.540,00 | 15.092,00 |
| 3 | Pasir pasang | M³ | 0,0450 | 400.000,00 | 18.000,00 |
| 4 | Semen warna/putih | KG | 1,3000 | 217.800,00 | 283.140,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2500 | 200.000,00 | 50.000,00 |
| 2 | Tukang batu | OH | 0,1250 | 150.000,00 | 18.750,00 |
| 3 | Kepala tukang | OH | 0,0130 | 155.000,00 | 2.015,00 |
| 4 | Mandor | OH | 0,0130 | 165.000,00 | 2.145,00 |
| Jumlah | 114.038.367,69 | ||||
| Jasa 10% | 11.403.836,77 | ||||
| Total | 125.442.204,46 | ||||
N.4 — PASANG LANTAI GRANITO UKURAN 60 X 60 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | lantai Granito 60 x 60 cm | BH | 3,0000 | 103.000,00 | 309.000,00 |
| 2 | Semen portland | KG | 9,8000 | 1.540,00 | 15.092,00 |
| 3 | Pasir pasang | M³ | 0,0450 | 400.000,00 | 18.000,00 |
| 4 | Semen warna/putih | KG | 1,3000 | 217.800,00 | 283.140,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2600 | 200.000,00 | 52.000,00 |
| 2 | Tukang batu | OH | 0,1300 | 150.000,00 | 19.500,00 |
| 3 | Kepala tukang | OH | 0,0130 | 155.000,00 | 2.015,00 |
| 4 | Mandor | OH | 0,0130 | 165.000,00 | 2.145,00 |
| Jumlah | 700.892,00 | ||||
| Jasa 10% | 70.089,20 | ||||
| Total | 770.981,20 | ||||
N.5 — PASANG LANTAI KERAMIK UKURAN 20 X 20 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Ubin keramik 20 x 20 cm KW 1 | BH | 26,5000 | 279.510,00 | 7.407.015,00 |
| 2 | Semen portland | KG | 10,4000 | 1.540,00 | 16.016,00 |
| 3 | Pasir pasang | M³ | 0,0450 | 400.000,00 | 18.000,00 |
| 4 | Semen warna/putih | KG | 1,6200 | 217.800,00 | 352.836,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,2700 | 200.000,00 | 54.000,00 |
| 2 | Tukang batu | OH | 0,1350 | 150.000,00 | 20.250,00 |
| 3 | Kepala tukang | OH | 0,0140 | 155.000,00 | 2.170,00 |
| 4 | Mandor | OH | 0,0140 | 165.000,00 | 2.310,00 |
| Jumlah | 7.872.597,00 | ||||
| Jasa 10% | 787.259,70 | ||||
| Total | 8.659.856,70 | ||||
N.6 — PASANG DINDING KERAMIK 20 X 25 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Dinding keramik 20 x 25 cm Roman | BH | 21,2000 | 556.600,00 | 11.799.920,00 |
| 2 | Semen portland | KG | 9,3000 | 1.540,00 | 14.322,00 |
| 3 | Pasir pasang | M³ | 0,0180 | 400.000,00 | 7.200,00 |
| 4 | Semen warna/putih | KG | 1,9400 | 217.800,00 | 422.532,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,4000 | 200.000,00 | 80.000,00 |
| 2 | Tukang batu | OH | 0,2000 | 150.000,00 | 30.000,00 |
| 3 | Kepala tukang | OH | 0,0200 | 155.000,00 | 3.100,00 |
| 4 | Mandor | OH | 0,0200 | 165.000,00 | 3.300,00 |
| Jumlah | 12.360.374,00 | ||||
| Jasa 10% | 1.236.037,40 | ||||
| Total | 13.596.411,40 | ||||
N.7 — PASANG DINDING KERAMIK 20 X 40 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Dinding keramik 20 x 40 cm | BH | 13,2500 | 907.500,00 | 12.024.375,00 |
| 2 | Semen portland | KG | 9,3000 | 1.540,00 | 14.322,00 |
| 3 | Pasir pasang | M³ | 0,0180 | 400.000,00 | 7.200,00 |
| 4 | Semen warna/putih | KG | 1,9400 | 217.800,00 | 422.532,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,4000 | 200.000,00 | 80.000,00 |
| 2 | Tukang batu | OH | 0,2000 | 150.000,00 | 30.000,00 |
| 3 | Kepala tukang | OH | 0,0200 | 155.000,00 | 3.100,00 |
| 4 | Mandor | OH | 0,0200 | 165.000,00 | 3.300,00 |
| Jumlah | 12.584.829,00 | ||||
| Jasa 10% | 1.258.482,90 | ||||
| Total | 13.843.311,90 | ||||
N.8 — PASANG DINDING GRANIT 30 X 60 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Ubin Granit 30 x 60 cm KW 1 | BH | 5,5556 | 51.450,00 | 285.835,62 |
| 2 | Semen portland | KG | 9,3000 | 1.540,00 | 14.322,00 |
| 3 | Pasir pasang | M³ | 0,0180 | 400.000,00 | 7.200,00 |
| 4 | Semen warna/putih | KG | 1,9400 | 217.800,00 | 422.532,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,4000 | 200.000,00 | 80.000,00 |
| 2 | Tukang batu | OH | 0,2000 | 150.000,00 | 30.000,00 |
| 3 | Kepala tukang | OH | 0,0200 | 155.000,00 | 3.100,00 |
| 4 | Mandor | OH | 0,0200 | 165.000,00 | 3.300,00 |
| Jumlah | 846.289,62 | ||||
| Jasa 10% | 84.628,96 | ||||
| Total | 930.918,58 | ||||
N.9 — PASANG DINDING KERAMIK 30 X 60 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Semen portland | KG | 9,3000 | 1.540,00 | 14.322,00 |
| 2 | Pasir pasang | M³ | 0,0180 | 400.000,00 | 7.200,00 |
| 3 | Semen warna/putih | KG | 1,9400 | 217.800,00 | 422.532,00 |
| 4 | Dinding keramik 30 x 60 cm Motif | BH | 5,5556 | 28.000,00 | 155.556,80 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,4000 | 200.000,00 | 80.000,00 |
| 2 | Tukang batu | OH | 0,2000 | 150.000,00 | 30.000,00 |
| 3 | Kepala tukang | OH | 0,0200 | 155.000,00 | 3.100,00 |
| 4 | Mandor | OH | 0,0200 | 165.000,00 | 3.300,00 |
| Jumlah | 716.010,80 | ||||
| Jasa 10% | 71.601,08 | ||||
| Total | 787.611,88 | ||||
N.10 — PASANG PLINT KERAMIK UKURAN 10 X 40 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Plint keramik 10 x 40 cm | BH | 2,6500 | 3.277,00 | 8.684,05 |
| 2 | Semen portland | KG | 1,1400 | 1.540,00 | 1.755,60 |
| 3 | Pasir pasang | M³ | 0,0030 | 400.000,00 | 1.200,00 |
| 4 | Semen warna/putih | KG | 0,1000 | 217.800,00 | 21.780,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0900 | 200.000,00 | 18.000,00 |
| 2 | Tukang batu | OH | 0,0900 | 150.000,00 | 13.500,00 |
| 3 | Kepala tukang | OH | 0,0090 | 155.000,00 | 1.395,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 67.139,65 | ||||
| Jasa 10% | 6.713,97 | ||||
| Total | 73.853,62 | ||||
N.11 — PASANG PLINT GRANIT UKURAN 10 X 60 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Plint Granit 10 x 60 Cm | BH | 1,7000 | 17.100,00 | 29.070,00 |
| 2 | Semen portland | KG | 1,1400 | 1.540,00 | 1.755,60 |
| 3 | Pasir pasang | M³ | 0,0030 | 400.000,00 | 1.200,00 |
| 4 | Semen warna/putih | KG | 0,1000 | 217.800,00 | 21.780,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0900 | 200.000,00 | 18.000,00 |
| 2 | Tukang batu | OH | 0,0900 | 150.000,00 | 13.500,00 |
| 3 | Kepala tukang | OH | 0,0090 | 155.000,00 | 1.395,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 87.525,60 | ||||
| Jasa 10% | 8.752,56 | ||||
| Total | 96.278,16 | ||||
N.12 — PASANG PLINT UKURAN 10 X 60 CM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Plint keramik 10 x 60 cm | BH | 1,7000 | 14.000,00 | 23.800,00 |
| 2 | Semen portland | KG | 1,1400 | 1.540,00 | 1.755,60 |
| 3 | Pasir pasang | M³ | 0,0030 | 400.000,00 | 1.200,00 |
| 4 | Semen warna/putih | KG | 0,1000 | 217.800,00 | 21.780,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0900 | 200.000,00 | 18.000,00 |
| 2 | Tukang batu | OH | 0,0900 | 150.000,00 | 13.500,00 |
| 3 | Kepala tukang | OH | 0,0090 | 155.000,00 | 1.395,00 |
| 4 | Mandor | OH | 0,0050 | 165.000,00 | 825,00 |
| Jumlah | 82.255,60 | ||||
| Jasa 10% | 8.225,56 | ||||
| Total | 90.481,16 | ||||
N.13 — PASANGAN BATU ALAM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Batu alam | M² | 1,1000 | 151.250,00 | 166.375,00 |
| 2 | Semen portland | KG | 11,7500 | 1.540,00 | 18.095,00 |
| 3 | Pasir pasang | M³ | 0,0350 | 400.000,00 | 14.000,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,6200 | 200.000,00 | 124.000,00 |
| 2 | Tukang batu | OH | 0,3500 | 150.000,00 | 52.500,00 |
| 3 | Kepala tukang | OH | 0,0350 | 155.000,00 | 5.425,00 |
| 4 | Mandor | OH | 0,3000 | 165.000,00 | 49.500,00 |
| Jumlah | 429.895,00 | ||||
| Jasa 10% | 42.989,50 | ||||
| Total | 472.884,50 | ||||
N.14 — PASANGAN KERAMIK MOTIF BATU ALAM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Dinding keramik 30 x 60 cm Motif | BH | 6,2500 | 28.000,00 | 175.000,00 |
| 2 | Semen portland | KG | 9,3000 | 1.540,00 | 14.322,00 |
| 3 | Pasir pasang | M³ | 0,0180 | 400.000,00 | 7.200,00 |
| 4 | Semen warna/putih | KG | 1,9400 | 217.800,00 | 422.532,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,6200 | 200.000,00 | 124.000,00 |
| 2 | Tukang batu | OH | 0,3500 | 150.000,00 | 52.500,00 |
| 3 | Kepala tukang | OH | 0,0350 | 155.000,00 | 5.425,00 |
| 4 | Mandor | OH | 0,3000 | 165.000,00 | 49.500,00 |
| Jumlah | 850.479,00 | ||||
| Jasa 10% | 85.047,90 | ||||
| Total | 935.526,90 | ||||
| KELOMPOK O |
O.1 — PENGECATAN BIDANG KAYU BARU DG PLAMIR+1LPS DSR+2LPS (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Cat meni kayu | KG | 0,2000 | 30.250,00 | 6.050,00 |
| 2 | Plamir kayu | KG | 0,1500 | 39.930,00 | 5.989,50 |
| 3 | Cat kayu/besi | KG | 0,1700 | 70.180,00 | 11.930,60 |
| 4 | Cat kayu/besi | KG | 0,2600 | 70.180,00 | 18.246,80 |
| 5 | Amplas | LBR | 0,5000 | 7.260,00 | 3.630,00 |
| 6 | Minyak cat/ thinner | LTR | 0,1000 | 16.500,00 | 1.650,00 |
| 7 | Kuas | BH | 0,0500 | 24.200,00 | 1.210,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0700 | 200.000,00 | 14.000,00 |
| 2 | Tukang cat | OH | 0,0900 | 150.000,00 | 13.500,00 |
| 3 | Kepala tukang | OH | 0,0060 | 155.000,00 | 930,00 |
| 4 | Mandor | OH | 0,0025 | 165.000,00 | 412,50 |
| Jumlah | 77.549,40 | ||||
| Jasa 10% | 7.754,94 | ||||
| Total | 85.304,34 | ||||
O.2 — PENGECATAN PLAFOND (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Plamir tembok | KG | 0,1000 | 550.000,00 | 55.000,00 |
| 2 | Cat tembok | KG | 0,1000 | 46.200,00 | 4.620,00 |
| 3 | Cat tembok | KG | 0,2600 | 46.200,00 | 12.012,00 |
| 4 | Amplas | LBR | 0,3000 | 7.260,00 | 2.178,00 |
| 5 | Kuas Roll | BH | 0,0150 | 30.250,00 | 453,75 |
| 6 | Bak Cat | BH | 0,0150 | 18.150,00 | 272,25 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0200 | 200.000,00 | 4.000,00 |
| 2 | Tukang cat | OH | 0,0630 | 150.000,00 | 9.450,00 |
| 3 | Kepala tukang | OH | 0,0063 | 155.000,00 | 976,50 |
| 4 | Mandor | OH | 0,0025 | 165.000,00 | 412,50 |
| Jumlah | 89.375,00 | ||||
| Jasa 10% | 8.937,50 | ||||
| Total | 98.312,50 | ||||
O.3 — PENGECATAN TEMBOK BARU DG PLAMIR (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Plamir tembok | KG | 0,1000 | 550.000,00 | 55.000,00 |
| 2 | Cat tembok | KG | 0,1000 | 46.200,00 | 4.620,00 |
| 3 | Cat tembok Exterior | KG | 0,2600 | 153.000,00 | 39.780,00 |
| 4 | Amplas | LBR | 0,3000 | 7.260,00 | 2.178,00 |
| 5 | Kuas Roll | BH | 0,0150 | 30.250,00 | 453,75 |
| 6 | Bak Cat | BH | 0,0150 | 18.150,00 | 272,25 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0200 | 200.000,00 | 4.000,00 |
| 2 | Tukang cat | OH | 0,0630 | 150.000,00 | 9.450,00 |
| 3 | Kepala tukang | OH | 0,0063 | 155.000,00 | 976,50 |
| 4 | Mandor | OH | 0,0025 | 165.000,00 | 412,50 |
| Jumlah | 117.143,00 | ||||
| Jasa 10% | 11.714,30 | ||||
| Total | 128.857,30 | ||||
O.4 — PELEBURAN BIDANG KAYU CAT RESIDU DAN TER TIAP 1 M2 (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Residu | LTR | 0,3500 | 726.000,00 | 254.100,00 |
| 2 | Kuas | BH | 0,0500 | 24.200,00 | 1.210,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,1000 | 200.000,00 | 20.000,00 |
| 2 | Mandor | OH | 0,0060 | 165.000,00 | 990,00 |
| Jumlah | 276.300,00 | ||||
| Jasa 10% | 27.630,00 | ||||
| Total | 303.930,00 | ||||
O.5 — PENGECATAN COATING BATU ALAM (M²)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Cumoir Water Proofing | KG | 0,3000 | 39.930,00 | 11.979,00 |
| 2 | Kuas | BH | 0,2000 | 24.200,00 | 4.840,00 |
| UPAH | |||||
| 1 | Pekerja | OH | 0,0200 | 200.000,00 | 4.000,00 |
| 2 | Tukang cat | OH | 0,0630 | 150.000,00 | 9.450,00 |
| 3 | Kepala tukang | OH | 0,0063 | 155.000,00 | 976,50 |
| 4 | Mandor | OH | 0,0025 | 165.000,00 | 412,50 |
| Jumlah | 31.658,00 | ||||
| Jasa 10% | 3.165,80 | ||||
| Total | 34.823,80 | ||||
| KELOMPOK P |
P.1 — PASANG INSTALASI LAMPU NYM 2X2,5 MM (TITIK)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| MATERIAL | |||||
| 1 | Kabel NYM 2x2,5 mm² | M' | 12,0000 | 11.000,00 | 132.000,00 |
| 2 | pipa listrik | Btg | 12,0000 | 4.537,00 | 54.444,00 |
| 3 | Fitting | BH | 1,0000 | 18.700,00 | 18.700,00 |
| 4 | Saklar tunggal | BH | 1,0000 | 20.790,00 | 20.790,00 |
| 5 | Lampu | BH | 1,0000 | 60.500,00 | 60.500,00 |
| 6 | Tee dos | BH | 1,0000 | 220.000,00 | 220.000,00 |
| 7 | Inbow doos | BH | 1,0000 | 220.000,00 | 220.000,00 |
| 8 | Sock | BH | 3,0000 | 110.000,00 | 330.000,00 |
| 9 | Klem conduit | BH | 9,0000 | 110.000,00 | 990.000,00 |
| 10 | Lastdop | BH | 3,0000 | 82.500,00 | 247.500,00 |
| 11 | Pleksiblle Pipe | M' | 1,0000 | 363.000,00 | 363.000,00 |
| 12 | Elbow | BH | 2,0000 | 275.000,00 | 550.000,00 |
| 13 | Paku, sekrup, fisher (10% harga conduit) | % | 0,1000 | 54.450,00 | 5.445,00 |
| UPAH | |||||
| 1 | Instalator | OH | 0,3000 | 150.000,00 | 45.000,00 |
| 2 | Pekerja | OH | 0,1500 | 200.000,00 | 30.000,00 |
| 3 | Mandor | OH | 0,0150 | 165.000,00 | 2.475,00 |
| Jumlah | 3.289.854,00 | ||||
| Jasa 10% | 328.985,40 | ||||
| Total | 3.618.839,40 | ||||
P.2 — PASANG INSTALASI STOP KONTAK TIAP 1 TITIK (TITIK)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| Data AHSP belum tersedia | |||||
| Jumlah | 0,00 | ||||
| Jasa 10% | 0,00 | ||||
| Total | 0,00 | ||||
| KELOMPOK Q |
Q.1 — MEMBUAT SALURAN AIR BUIS BETON 0,5 DIA 20 CM DINDING BATA 15-25 CM (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| Data AHSP belum tersedia | |||||
| Jumlah | 0,00 | ||||
| Jasa 10% | 0,00 | ||||
| Total | 0,00 | ||||
Q.2 — MEMBUAT SALURAN AIR DARI BATU KALI LEBAR BAWAH 80 CM TINGGI 100 CM TIAP 1 (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| Data AHSP belum tersedia | |||||
| Jumlah | 0,00 | ||||
| Jasa 10% | 0,00 | ||||
| Total | 0,00 | ||||
Q.3 — MEMBUAT SALURAN AIR DARI BATU KALI LEBAR BAWAH 30 CM TINGGI 60 CM TIAP 1 (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| Data AHSP belum tersedia | |||||
| Jumlah | 0,00 | ||||
| Jasa 10% | 0,00 | ||||
| Total | 0,00 | ||||
Q.4 — PLAT DUIKER PINTU MASUK, LEBAR SALURAN 1 M (TEBAL PLAT 15 CM) (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| Data AHSP belum tersedia | |||||
| Jumlah | 0,00 | ||||
| Jasa 10% | 0,00 | ||||
| Total | 0,00 | ||||
Q.5 — PLAT DUIKER PINTU MASUK, LEBAR SALURAN 0,5 M (TEBAL PLAT 10 CM) TIAP 1 M' (M)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| Data AHSP belum tersedia | |||||
| Jumlah | 0,00 | ||||
| Jasa 10% | 0,00 | ||||
| Total | 0,00 | ||||
Q.6 — MEMBUAT JALAN BETON + WIREMESH (M³)
| No | Uraian | Sat | Koef | Harga | Sub Total |
|---|---|---|---|---|---|
| Data AHSP belum tersedia | |||||
| Jumlah | 0,00 | ||||
| Jasa 10% | 0,00 | ||||
| Total | 0,00 | ||||
I.SLOOF — COR SLOOF BETON BERTULANG 15 × 20 CM (M³)
| Pembesian (besi 12 = ) | 2.121.344,23 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 3.816.163,73 |
II.SLOOF — COR SLOOF BETON BERTULANG 20 × 20 CM (M³)
| Pembesian (besi 12 = ) | 3.356.048,95 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.050.868,45 |
III.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
IV.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 2.512.660,15 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 4.207.479,65 |
V.SLOOF — COR SLOOF BETON BERTULANG 30 × 40 CM (M³)
| Pembesian (besi 12 = ) | 1.811.586,78 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 3.506.406,28 |
VI.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.623.173,55 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.317.993,05 |
VII.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
VIII.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
IX.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
X.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
XI.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
XII.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
XIII.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
XIV.SLOOF — COR SLOOF BETON BERTULANG 20 × 30 CM (M³)
| Pembesian (besi 12 = ) | 3.666.012,35 |
| Beton Struktur (TOTAL I.2) | 1.370.644,00 |
| Bekisting (TOTAL I.11) | 324.175,50 |
| TOTAL COR SLOOF | 5.360.831,85 |
| GRAND TOTAL RAB | 425.849.702,59 |